Skip to content
Discuss Your Project
  1. Home
  2. Blog
  3. Occupancy permit in Turkey (iskan): what it is and how to get it

Occupancy permit in Turkey (iskan): what it is and how to get it

13 min read

In Turkey, an occupancy permit, known locally as iskan (yapı kullanma izin belgesi), is the official permission to use a completed building. It confirms that the building was built in line with its building permit and approved drawings. The municipality or governorship that issued the building permit grants it. Under the Zoning Law, the authority must decide within 30 days. As a rule, buildings without it cannot receive electricity, water or sewerage services.

What is an occupancy permit (iskan) and how does it differ from a building permit?

A building permit is needed to start construction; an occupancy permit is needed to use the finished building. The building permit approves the design against the zoning plan and regulations. Iskan confirms that the building was completed in line with that permit and its annexes, and that its use poses no technical risk. The same authority issues both documents.

TopicBuilding permitOccupancy permit (iskan)
When is it obtained?Before construction startsWhen the whole building, or a usable part of it, is finished
Basis in the Zoning LawArticles 21 and 22Articles 30 and 31
Issuing authorityMunicipality or governorshipThe authority that issued the building permit
Application annexesTitle deed; architectural, structural, electrical and mechanical drawingsSite supervisor or building inspection firm reports, energy identity certificate, photographs
Legal deadline30 days for a complete file; if incomplete, written notice within 15 days30 days; if no decision, permission is deemed granted
Time limitConstruction starts within 2 years; permit void if not finished within 5 years including that periodMust be issued within the 5-year permit period
What it allowsBuilding worksUsing the building; electricity, water and sewerage; automatic conversion of kat irtifakı to kat mülkiyeti
Building permit and occupancy permit compared, as of November 2026. Source: Zoning Law No. 3194 and Planned Areas Zoning Regulation (2017); title deed: Condominium Law Article 10

The Planned Areas Zoning Regulation defines it as an approved certificate that allows use of the building. It shows the building was completed in line with its permit drawings. The Zoning Law adds a rule on dates: the completion date of a building is the date its occupancy permit is issued.

The permit is issued online on a standard ministry form and recorded in the national address database under a tracking number. The form lists the building's independent units by use, such as residential or shop, and records each use separately. This record shows what each part of a building may legally be used for.

Where is the occupancy permit issued and how long does it take?

The occupancy permit is issued by the authority that granted the building permit: the municipality or the governorship. The owner submits the application. Under the Planned Areas Zoning Regulation, the permit is issued within 30 days if the building complies. The Zoning Law states that if no decision is made within 30 days, use of the whole building or its finished part is deemed permitted.

  1. CompletionThe building is finished in line with its permit and drawings within the 5-year permit period.
  2. Reports and documentsSite supervisor or building inspection firm reports, an energy identity certificate issued by an authorised expert and photographs of the building are prepared.
  3. Social security clearanceBefore issuing the permit, the authority requests a document showing no debt to the Social Security Institution (SGK).
  4. ApplicationThe owner applies to the issuing authority with a petition or the authority's standard form.
  5. InspectionThe authority checks whether the building was completed in line with its permit, annexes and technical and health rules.
  6. DecisionIf compliant, the permit is issued within 30 days; if not, the owner is asked to fix the deficiencies and the process repeats.
  7. Title deedThe permit reaches the cadastre office through the Spatial Address Registration System (MAKS); the land registry records the change of property type and the switch to condominium ownership automatically.
Steps and legal deadlines for an occupancy permit application in Turkey. Source: Zoning Law Articles 29–30, Planned Areas Zoning Regulation Articles 64–65, Law No. 5510 Article 90, Condominium Law No. 634, Article 10

The inspection goes beyond the drawings. Under the regulation, the authority checks that aerial and cable installations allow several service providers. It checks for sign space on commercial buildings, and for a waste separation chute and the use of renewable energy where required. In housing estates, grey water tanks and external security cameras are also checked.

The competent authority is not always the municipality. In areas governed by special laws, such as tourism centres, only those Zoning Law provisions that do not conflict with the special law apply. For buildings assigned to the Ministry of Environment, Urbanisation and Climate Change, its provincial directorates handle permits. Confirm the competent authority and the current rules with that authority before applying.

How do you get an occupancy permit (iskan) in Turkey, and which documents are needed?

The documents that may be requested for iskan are limited by regulation. Article 65 of the Planned Areas Zoning Regulation sets the list. Beyond a petition or form, site supervisor or inspection firm reports, an energy identity certificate and photographs, no document may be requested. The social security clearance comes from a separate law.

DocumentStatus in the applicationLegal basis
Petition or the authority's standard formRequiredRegulation Art. 65/1
Site supervisor or building inspection firm reportsRequiredRegulation Art. 64/1, 65/1
Energy identity certificateRequiredRegulation Art. 64/1, 65/1
Photographs of the buildingRequiredRegulation Art. 64/1, 65/1
Proof of no debt to the Social Security InstitutionAuthority must request itLaw No. 5510 Art. 90
Street numbering and sewer connection documentsNot requested from the applicant; municipal units share them electronicallyRegulation Art. 65/5–6
Gas compliance certificate, fire safety (fire brigade) report, shelter reportNot requested from the applicantRegulation Art. 65/7
Material delivery notes and invoices; approvals of foundation, soil and insulation inspectionsNot requested from the applicantRegulation Art. 65/7
Property purchase tax clearance, tax debt letter, occupation fee letter, municipal tax and fee receiptsNot requested from the applicantRegulation Art. 65/7
Documents already held by the authority or shared electronicallyNot requested againRegulation Art. 65/2–4
Documents that may be requested for an occupancy permit in Turkey, and those that may not be requested from the applicant, as of November 2026. Source: Planned Areas Zoning Regulation, Articles 64–65; social security clearance: Social Insurance and General Health Insurance Law No. 5510, Article 90

The table corrects a common mistake. Several iskan guides list a fire brigade report, a tax clearance letter or fee receipts as application documents. The regulation forbids requesting these from the applicant and requires authorities to share such information electronically. The ban does not remove tax and fee obligations.

An energy identity certificate (Enerji Kimlik Belgesi, EKB) shows a building's energy demand and class. It is issued by authorised energy identity certificate experts. Site supervisor reports confirm that the building follows its permit drawings and technical and health rules, and that compliant materials were used.

The signing stage has a safeguard too. Site supervisors are legally required to sign the occupancy permit within their fields. If the contractor, site manager or architect cannot be reached for reasons such as death or a conviction, the permit can be issued without their signatures. The condition is that the authority, the site supervisors and the owner have documented timely completion in line with the permit.

What happens if a building has no iskan?

A building without iskan is not legally open for use. Under the Zoning Law, it cannot receive electricity, water or sewerage services until the permit is issued. The automatic conversion of the title to condominium ownership does not take place. Some businesses, such as hotels, cannot obtain an operating licence.

  • Permit period. Iskan must be obtained within the 5-year building permit period. Under the Zoning Law, a permit lapses if the building is not finished within 5 years, including the start period. A new permit is then required.
  • Operating licence. The Regulation on Workplace Opening and Operating Licences requires iskan for special building types, such as hotels, cinemas, theatres, wedding halls, hammams and saunas. The same applies to bakeries and to fuel, LPG, LNG and CNG stations.
  • Accommodation. A provision added on 11 December 2025 separately requires accommodation premises to hold an occupancy permit and a fire brigade report.
  • Liability. Deemed permission after 30 days does not cure violations. It does not release the owner from liability for breaching the permit, nor from taxes, duties and fees.

For hotel investors, this rule directly affects the opening schedule. Because the operating licence is not granted without iskan, the permit period should be built into the programme from the start. For room planning, see our guide on hotel room sizes. For details, consult the Regulation on Workplace Opening and Operating Licences and the local municipality.

What is a partial occupancy permit?

A partial occupancy permit is iskan granted for parts of a building that become usable before the whole building is finished. The Zoning Law expressly allows this. Under the regulation, the common areas serving those parts must be complete and usable, and the building must have no breach of the rules.

Units with a partial permit can receive electricity, water and sewerage; the rest of the building cannot until it is permitted. A similar rule applies to multi-block sites. Where a plot has several buildings, deviations in some buildings do not block iskan for the others.

For a building completed in line with its permit, the consent of all plot owners is not required for iskan. This prevents the permit for a finished building from depending on each owner's approval. Common areas still decide a partial permit. For example, a unit cannot be permitted before the stairs or lift serving it are finished.

Why does iskan matter in an interior design project?

Iskan sets two limits for an interior design project in an existing building: the registered use of the space and the scope of alterations. Of Picco Architecture's 140 projects in Turkey, 126 are in the healthcare sector. In our view, the building's occupancy permit is one of the first documents to check before such a project starts.

  • 140projects in Turkey, in 23 cities
  • 126healthcare sector projects
  • 96polyclinic projects
  • 58turnkey healthcare projects
  • 402.5 m²median area of healthcare projects
Picco Architecture's projects in Turkey: number, type, scope and area. Source: Picco Architecture project archive, November 2026

As of November 2026, Picco Architecture's archive holds 140 projects in 23 Turkish cities, 72 of them in Antalya. Of the 126 healthcare projects, 96 are polyclinics, 19 are private practices, 6 are oral and dental health centres and 1 is a dental hospital. The other 4 are a hair transplant centre, a dental laboratory, a beauty centre and a dental supply depot.

The healthcare projects range from 86 to 3,000 m², with a median of 402.5 m². 58 were delivered turnkey, 38 as design with site supervision and 30 as design only. For example, the UST Oral and Dental Health Polyclinic in Antalya is recorded at 2,000 m² and was delivered turnkey. See our healthcare projects for more.

Why does the registered use matter? The Planned Areas Zoning Regulation treats a change in a unit's use as a major alteration that requires a permit. Converting a unit registered as residential into a business therefore needs an alteration permit. If you are budgeting a clinic, our guide on the cost of opening a dental practice covers the items in detail.

Two new rules also affect the scope of alterations. Under an August 2025 amendment, alterations in a building with iskan are not blocked by the absence of a zoning plan in force. The outline, footprint, floor area ratio, floor area, eaves level and use must stay the same. Structural and fire safety measures must also be taken.

A July 2026 amendment eased the rules for older buildings. Where iskan predates the Planned Areas Zoning Regulation of 2017, major alterations can follow the rules in force on the building permit date. Floor area ratio, floor area, use, other units' land shares, eaves level and setbacks must be kept, and the structure must not be weakened. Current fire, earthquake, insulation and energy efficiency measures must also be taken. After any alteration that changes energy performance, the energy identity certificate must be renewed; buildings under 1,000 m² outside municipal adjacent areas are exempt.

Let’s discuss your project.

Leave a few details and our team will get in touch to discuss the scope, the budget and the next steps.

On-site surveys of existing premises are free of charge.

Prefer to talk now? WhatsApp Call Picco Architecture: +90 850 532 10 50

Contact Details
How did you hear about us? (Optional)

Please confirm that you have read the privacy notice to continue.

Frequently asked questions

Can a building without iskan get electricity and water?

As a rule, no. Under Article 31 of the Zoning Law, buildings without an occupancy permit receive no electricity, water or sewerage services until the permit is issued. The Planned Areas Zoning Regulation adds communication and similar services and makes the service provider liable if it supplies an unpermitted building. With a partial permit, only the permitted units receive these services.

Does a shop need a separate iskan?

The occupancy permit covers the whole building or its usable parts. The certificate records each unit by use, such as residential or shop. If the shop is to be used before the building is finished, a partial permit can be requested. For a business licence, the authority accesses the iskan record through the Identity Sharing System. Buildings with a commercial building registration certificate (yapı kayıt belgesi) can be licensed without iskan if safety conditions are met. This applies until the building is rebuilt or included in urban renewal.

What if the contractor's debts block the iskan?

Article 28 of the Zoning Law provides a specific route. Completion must be recorded in a report signed jointly by the owner, the site supervisors and the authority's staff. If the contractor's tax and social insurance debts then block the permit, an owner who is not the contractor can apply. The authority verifies the situation and issues the permit. Seek legal advice for your own case.

Is an energy identity certificate required for iskan?

Yes. The Planned Areas Zoning Regulation lists an energy identity certificate, issued by authorised experts, as an application annex. An amendment of 16 May 2026 added a new requirement. From 1 January 2027, new buildings of 10,000 m² or more must also submit a building life-cycle analysis certificate at the iskan stage.

How does the title deed change after iskan?

Automatically. Under Article 10 of the Condominium Law, amended in 2021, the occupancy permit is uploaded to the Spatial Address Registration System. It then goes electronically to the cadastre office. The land registry records the change of property type without asking for other documents. If the property carries a construction servitude (kat irtifakı), it is converted to condominium ownership (kat mülkiyeti) free of the registry service fee.

Planning iskan at the start of a project protects both the opening date and later alteration options. For choosing a space and planning works in Antalya, see our Antalya interior architect guide. To review a building's iskan and registered use alongside your project, contact us.