An architect is the professional who designs a building around its users' needs, planning rules and budget, and who, where the contract provides for it, checks that the design is built correctly. What does an architect do in practice? The architect studies the site and the brief, prepares the preliminary and final designs, and draws and signs the architectural project used for the building permit. The architect then develops working drawings and details and, if engaged for supervision, checks on site that construction follows them.

What does an architect do on a building project?

An architect makes and documents the architectural decisions of a project, from first sketch to completed building. The core output is the architectural project: the building's position on the plot, its massing, floors, internal layout, façades and materials. The architect also coordinates these drawings with the engineers who prepare the structural, electrical and mechanical designs.

In Turkey, the Chamber of Architects, part of the Union of Chambers of Turkish Engineers and Architects (TMMOB), publishes a services specification dated 2011. It groups the work an architect may design, supervise and sign as author into four areas:

  • Architectural design. Architectural projects, measured surveys, restitution and restoration, interior space planning, landscaping and urban design.
  • Delivery and management. Professional site supervision, construction management, design and site coordination, site management, technical responsibility and building inspection.
  • Consultancy. Feasibility studies, briefing, tender documents and specifications, expert witness work and competition juries.
  • Artistic work. Models, three-dimensional visuals and the selection of artworks.

Not every architect offers every service on the list. Some work only in a design studio; others work on site, in the public sector or for building inspection firms. What they share is that architectural decisions are recorded in drawings, reports and calculations, and a signed document carries legal responsibility.

At which stages of a project is an architect involved?

An architect can be involved at every stage, from defining the client's needs to the final acceptance of the building. The Chamber of Architects' specification divides design services into preparation and site study, preliminary design, final design, working drawings and details. Site supervision, as-built drawings and handover are listed as separate services.

  1. Preparation and site studyThe client's needs and resources are defined; zoning status, cadastral and ground data are collected.
  2. Preliminary designLayout, levels, parking and area calculations are resolved; plans, at least two sections and elevations are usually drawn at 1:100.
  3. Final designFollowing the approved preliminary design, fire, seismic, energy performance, materials and the room schedule are fixed.
  4. Working drawingsThe construction set, usually at 1:50, coordinated with the structural design; it is the basis for quantities and cost estimates.
  5. System, assembly and fabrication detailsJunctions of façade, roof, stairs, windows and wet areas, and elements to be made in a workshop, are drawn.
  6. Specifications, quantities and estimateTechnical specifications are written; quantities and the approximate cost are calculated.
  7. Professional supervisionSite visits check that construction follows the drawings and specifications; extra details are issued if needed.
  8. As-built drawings and acceptanceIf the contract requires it, the built state is recorded; the architect lists defects before acceptance and signs the acceptance report with the contractor and the client.
Stages of architectural services and what each stage covers. Source: TMMOB Chamber of Architects, Architectural Services Specification and Minimum Fee Schedule, 2011

The specification assigns each stage a share of the architectural design fee. Working drawings carry the largest share at 30%; the final design takes 20%, and system, assembly and fabrication details together take another 20%. Preparation, preliminary design, working drawings and system and assembly details are compulsory stages, worth 60% in total. The final design is not a compulsory stage in the specification.

Split of the architectural design fee by stage; detail items and specification, quantity and estimate items are combined. Source: TMMOB Chamber of Architects, Architectural Services Specification and Minimum Fee Schedule, 2011, Article 7
Show the data as a table
StageShare (%)
Preparation and site study5
Preliminary design15
Final design20
Working drawings30
System, assembly and fabrication details20
Specifications, quantities and estimate10

In our view, this split has a practical meaning. The preliminary design is only 15% of the fee, yet it sets the frame for every later stage. A decision left open at that point costs more to change in the working drawings or on site.

The building permit in Turkey also rests on the architect's drawings. Under the Planned Areas Zoning Regulation, the "implementation projects" are the architectural, structural, electrical and mechanical designs. After the permit, the process ends with building inspection and the occupancy permit, which we explain in our guide to the Turkish occupancy permit.

Which drawings does an architect sign in Turkey?

In Turkey, the architect prepares and signs, as project author, the architectural project attached to the building permit. The Planned Areas Zoning Regulation states that architects prepare this project in line with the local zoning plan, the parcel plan and the regulation itself. Architects may also sign measured surveys, restoration and alteration projects, and some supplementary designs.

The regulation lists what the architectural project contains:

  • a site plan, a unit allocation table for condominium title and an area schedule;
  • plans of every floor, including basements, and a roof plan;
  • at least two sections, one through the common stair, and enough elevations;
  • an excavation calculation and parking, shelter and tree calculations.

Supplementary designs such as the preliminary lift design, the thermal and waterproofing design and the noise protection report are left to architects and engineers. Structural, electrical and mechanical designs belong to the relevant engineers. An architect who takes on design or technical responsibility must be registered with the Chamber of Architects and hold an office registration.

Which buildings require an experienced architect?

A provision added to the regulation in May 2023 sets an experience requirement for new public-access buildings in municipalities of more than 50,000 people. The architect who authors the project must have at least 5 years of experience. The architect must also document active work on at least 4 different permitted buildings totalling at least 10,000 m².

The requirement covers buildings such as government buildings, places of worship, education, healthcare, cultural and entertainment buildings, accommodation, shopping centres, transport stations, and office and commercial buildings. Buildings classified for reasons of state security are excluded. So are buildings in areas covered by the conservation law (No. 2863), the disaster-risk regeneration law (No. 6306) or other special laws. Half the criteria are enough for architects with a thesis-based postgraduate degree in architecture; the rule took effect on 1 July 2023.

This section is not legal advice. Please confirm the current text of the Planned Areas Zoning Regulation with the municipality or with Turkey's Ministry of Environment, Urbanisation and Climate Change.

What is the difference between an architect and a civil engineer?

The main difference between an architect and a civil engineer is the part of the project each is responsible for. The architect designs the building's spaces, massing and façades and signs the architectural project. The civil engineer calculates the load-bearing structure in line with the architectural project and the soil survey, and signs the structural design. In Turkey, each rests on its own degree and its own TMMOB chamber.

TopicArchitectCivil engineerInterior architect
Basis of the titleDegree in architecture (Law No. 3458)Degree in civil engineering (Law No. 3458)Bachelor's degree in interior architecture
Professional chamberTMMOB Chamber of ArchitectsTMMOB Chamber of Civil EngineersTMMOB Chamber of Interior Architects
Design in the permit processArchitectural projectStructural design; soil and foundation survey (with geological and geophysical engineers)Interior project for three building types only, before occupancy
Experience rule in the regulation5 years for new public-access buildings in municipalities above 50,000 people (half for a thesis-based postgraduate degree)At least 3, more than 5 or more than 7 years by storey count, for buildings of five or more storeys excluding the ground floorNot defined
Site manager rolePermittedPermitted; only civil engineers for work such as piling, shoring and seismic isolationNot among the professions listed in the regulation
Comparison of title, professional chamber and design responsibility for architects, civil engineers and interior architects in Turkey, as of November 2026. Source: Planned Areas Zoning Regulation, Article 57, Law No. 3458 on Engineering and Architecture and the Regulation on Site Managers (2019)

Turkey's Law No. 3458 on Engineering and Architecture, dating from 1938, ties the titles of architect and engineer to a degree; a person without one may not sign under those titles. The law does not separate the two professions' powers. That separation comes from zoning legislation, which states who prepares which design.

The two professions work side by side on most projects. The regulation requires the structural design to follow the architectural project, and the Chamber's specification expects the architect's working drawings to include the structural design's dimensions. In our view, the two disciplines should start agreeing at the preliminary design stage. We cover the interior architect's role in our article what an interior architect does.

What does an architect do on a construction site?

On a Turkish construction site, an architect can hold one of three main roles: supervising architect for the client, site manager for the contractor, or inspecting architect for a building inspection firm. Each role answers to a different party. The contract and permit documents show which role an architect holds.

  • Supervising architect. Checks for the client that work follows the drawings, specifications and standards, issues extra details and gives instructions. The Chamber's specification defines this as a separate service called professional supervision.
  • Site manager. The technical staff member who runs the works for the contractor. Under the Regulation on Site Managers, architects may act as site managers; the role lasts from the building permit to the occupancy permit.
  • Inspecting architect. Under Law No. 4708 on Building Inspection, an architect who holds an inspector's certificate from the Ministry and works for a building inspection firm. The firm's job is to check that the building matches its permit and attachments.

In our view, an architect acting as both the contractor's site manager and the client's supervisor on the same job risks a conflict of interest. The contract should therefore separate these roles from the start and state who signs which document.

What scale of projects does Picco Architecture work on?

As of November 2026, Picco Architecture's archive holds 156 project records in 8 countries and 31 cities. Of these, 131 are in the healthcare category and 14 in the hotel category, including sales offices and a trade fair stand; the rest are social, residential and education projects. The 131 healthcare records have a median area of 400 m², ranging from 86 m² to 3,000 m².

0102030201520172019202120232025202612
Distribution by year of the 142 project records with a year; the 2026 figure runs to November. Source: Picco Architecture project archive, November 2026
Show the data as a table
YearProjects
20153
20163
20178
20183
20199
202013
202126
202214
202319
202423
20259
202612

Of the 142 records with a year, 82, or about 58%, date from 2021–2024; the busiest year was 2021 with 26 records. Of the 139 projects with a recorded scope, 58 were turnkey delivery and 41 were design and site supervision. In our view, this shows that most of our projects continued on site: together, the two groups make 99 projects, about 71% of those with a recorded scope.

A list of completed work is in our references, and our practice is described on the about page. Healthcare projects are shown on our healthcare projects page.

In our view, when a clinic or hotel floor is designed inside an existing building, the first step is to see the approved architectural project and the occupancy permit. If the layout, wet areas or use will change, these documents show early which permits will be needed.

Let’s discuss your project.

Leave a few details and our team will get in touch to discuss the scope, the budget and the next steps.

On-site surveys of existing premises are free of charge.

Prefer to talk now? WhatsApp Call Picco Architecture: +90 850 532 10 50

Contact Details
How did you hear about us? (Optional)

Please confirm that you have read the privacy notice to continue.

Frequently asked questions

Is "architect" a protected title in Turkey?

Yes. Turkey's Law No. 3458 on Engineering and Architecture recognises only the titles "mimar" (architect) and "yüksek mimar" (literally "higher architect") and ties them to a degree. A person without the required document may not sign under the title. In everyday Turkish, "exterior architect" is sometimes used to distinguish architects from interior architects, but it is not a legal title.

What do you need to work as an architect in Turkey?

In Turkey, the title of architect comes from a degree in architecture under Law No. 3458; the law sets an extra document for degrees obtained abroad. An architect preparing permit drawings must be registered with the Chamber of Architects and hold an office registration. For new public-access buildings in municipalities above 50,000 people, at least 5 years of experience is also required; half the criteria suffice for architects with a thesis-based postgraduate degree in architecture.

Are the requirements different in Europe and the United States?

Yes, they vary by country. According to the Architects' Council of Europe (ACE), automatic recognition in the EU requires five years of study, or four years plus a supervised two-year traineeship. According to the US Bureau of Labor Statistics, every state requires architects to be licensed. The usual route is a degree, a paid internship and the Architect Registration Examination.

How long is an architect liable for a design in Turkey?

Under Law No. 4708 on Building Inspection, project authors are liable, in proportion to their fault, for damage caused by work that breaches the permit, its attachments or technical rules. The period runs from the date of the occupancy permit: 15 years for the load-bearing structure and 2 years for other parts. The liability is owed to the building owner and the relevant authority. These are the periods under Law No. 4708; this is not legal advice, so please confirm the current text.

What should you bring to a first meeting with an architect?

In our view, bringing the title deed or lease, zoning information, any approved drawings of the building, a list of users and needs, and a budget range speeds up the process. The Chamber of Architects' specification also expects the client's needs, zoning status, cadastral and ground data to be gathered at the preparation stage. Missing documents can mean the preliminary design starts from a wrong assumption.

So what does an architect do, in short? An architect turns a need into a buildable, documented project that complies with planning rules, and follows its construction. To discuss at which stage your project needs an architect, please contact us.